How long can the division take to notify an applicant about a variance decision if it does not involve an alternative procedure?

30 days

60 days

The correct choice is 60 days because regulatory frameworks often establish standardized timelines for processing applications, including those for variances. In this particular context, if the division does not utilize an alternative procedure, 60 days is typically the maximum time allowed to notify applicants regarding the decision on their variance request. This duration helps ensure that all necessary reviews and considerations are made to assess the application thoroughly, while also providing a reasonable timeline for applicants to expect feedback.

90 days

45 days